August 28, 2012
Day 8 of BWBL field construction is in the
books! We were able to get the right field wall up, as well as the
start of the second layer of the left field wall. All of the four foot
posts are primed and ready for hanging. The majority of the field side
of the first base dugout was also painted today. Thanks to Ryan Hart, Matthew Morgan, Kelly Chamberlain, Deidre, Andy Peck, and my Dad for the help today.
Work will continue tomorrow and Thursday from 5 to dark, Friday from 8
am to dark, and Saturday from 8 am to 5 pm. Stop on by and lend a hand!
If you know you can make it, shoot me a message so we know who all is
coming, but you can also just show up, too!
No comments:
Post a Comment